Ehrenfried-Walther-von-Tschirnhaus-Gymnasium

The high school in Dresden South-West with the new construction of a three-field sports gym shows a combination of the application of the Assessment System for Sustainable Building  with regard to the complete modernization down to the construction and the extension with new buildings.

Urheber: Merkla Architektur

Steckbrief

Art der Maßnahme
New building
Gebäudetyp
School
Baujahr (Fertigstellung)
2019
Bauherr:in

Landeshauptstadt Dresden, STESAD GmbH

 

Architekt:in

ARGE RBZAB Raum und Bau GmbH + AGZ Zimmermann Architekten GmbH

Fachplaner:in
  • Project manager: STESAD GmbH
  • Structural engineering: Leonhardt, Andrä und Partner, Beratende Ingenieure VBI AG
  • TGA: INNIUS Dö GmbH
  • Outdoor facilities: Storch Landschaftsarchitekten
  • Building physics: Genest und Partner Ingenieurgesellschaft mbH
  • Fire protection: Engineering office for structural fire protection
Zertifikat und Systemvariante
Silber (BNB)
BNB_UN13 und BNB_BK13
Auditor:in/ Nachhaltigkeitskoordinator:in
Dipl.-Ing. Nadine Merkla, M. Arch.
Dipl.-Ing. Nadine Merkla, M. Arch.

Gesamt-Erfüllungsgrad ( % ) / nach Hauptkriteriengruppen

Gesamt-Erfüllungsgrad (%)
68 %
Ökologische Qualität
80 %
Ökonomische Qualität
81 %
Soziokulturelle / funktionelle Qualität
58 %
Technische Qualität
60 %
Prozessqualität
55 %
Standortmerkmale
53 %

Flächen

BGF
18.715 m²

NGFa

16.118 m²
NF
11.257 m²

Energie

Primärenergiebedarf (EnEV)
New building: 41 kWh/(m²a) Old building: 38 kWh/(m²a) Sports hall: 41 kWh/(m²a)
Unterschreitung EnEV
56,9% (EnEV2014)
Anteil erneuerbarer Primärenergie am Gesamtprimärenergiebedarf (%)
16,2%

Ökobilanz (GWP) in kg CO2-Äqu./m²NGFaa

32,7

Kosten

Barwert, gesamt, pro m² BGF, netto
Cash value, total 1,800 €/m²BGF

Besondere Merkmale

Allgemein

The new extension encloses an atrium in a U-shape on the upper floors, so that the classrooms on the inside of the building are also sufficiently well lit. Below the atrium on the first floor is the spacious assembly hall, which is additionally lit by skylights. An integrated stage makes the room multifunctional.

The listed old building was initially completely and extensively gutted and renovated with regard to its former material loads. The aim for all three parts of the building was to create a school complex with very good indoor air quality.

Both the actual hall area of the sports hall and the changing rooms are located in the underground area, so that the upper grandstand area for spectators could be implemented barrier-free.

Energetische Qualität und Konzept

The school campus is supplied by the district heating network of Dresdner Stadtwerke, which can demonstrate a very high proportion of renewable energy (>95%).

Thanks to the sustainable, all-round approach and project support, it was possible to achieve good interior quality in terms of thermal and acoustic comfort.

Weitere Besonderheiten

The two new buildings were constructed as a solid reinforced concrete structure. The facades are ventilated and clad with fiber cement and aluminum panels. Behind the pilaster strips of the school extension are narrow opening casements, which can be used for overnight cooling without posing a safety risk.

Monumental elements of the old building that required protection, such as the facade, windows, door portals, banisters and the former main entrance area, were carefully renovated or reconstructed in close consultation with the Office for the Preservation of Monuments.